Houston Remodeling Project Timelines
Understanding remodeling timelines helps Houston homeowners plan logistics. Tell Projects provides detailed schedules with milestone dates for every project.
Typical Project Durations
- Kitchen Remodel (Standard): 8-12 weeks total - Permits (2 weeks), demolition (3 days), rough-in (1-2 weeks), cabinet install (3 days), countertops (2 weeks lead time), finish work (1 week)
- Bathroom Remodel: 4-6 weeks - Permits (2 weeks), demolition (2 days), plumbing/electrical rough-in (1 week), tile work (1 week), vanity/fixtures (1 week), final inspection
- Home Addition: 16-24 weeks - Plans/permits (4-6 weeks), foundation (2 weeks), framing (3-4 weeks), rough-in/inspections (2-3 weeks), drywall (2 weeks), finishes (4-6 weeks)
- Minor Updates: 2-4 weeks for cabinet refacing, countertop replacement, or flooring
Houston-Specific Factors: Permit review 7-14 days, inspections scheduled 24-48 hours advance, material delays 1-2 weeks (especially cabinets and countertops). Tell Projects builds buffer time into schedules.